Commercial Electrical Services · Pillar Guide
Commercial kitchen circuits, hood interlocks, walk-in compressors, POS dedicated outlets — the electrical scope that determines whether your restaurant opens on time.

Restaurant electrical is the most demanding commercial TI subcategory because the coordination overhead is enormous. A typical 4,000 sq ft full-service restaurant has 30-50 dedicated circuits — each cooking appliance, each refrigeration unit, each major kitchen tool gets its own. The circuits have to be sized to the specific equipment the operator is installing, which means we need equipment specs from the kitchen supplier BEFORE we pull permit.
The most common preventable issue on restaurant TI electrical is spec mismatch — the contractor installs circuits sized for equipment the operator changed mid-project, and the new equipment doesn't match. The fix is more expensive than getting it right the first time. We coordinate directly with the kitchen equipment vendor (Hobart, True, Vulcan, etc.) to confirm voltage, amperage, and connection requirements before any circuit work happens.
Restaurant electrical work covers the scope unique to food service properties — kitchen equipment circuits, hood interlocks, refrigeration compressors, customer-facing electrical (lighting, music, POS), and the inspection sequencing required for health department signoff and opening.
California Mechanical Code 508.1.1 requires hood exhaust fans to interlock with cooking equipment — meaning the fan runs automatically whenever cooking equipment is energized. Implementation typically uses a contactor or relay tied to the hood control circuit. Missing this is the most common reason for restaurant inspection failure.
Walk-in cooler and freezer compressors typically need 3-phase circuits — sizing varies by compressor (Bohn, Heatcraft, Kolpak are common brands). Each unit needs its own dedicated circuit; freezer compressors need slightly higher amperage than coolers. We pull manufacturer specs before sizing.
For the broader context this guide supports, see our Commercial Electrical Services overview.
Restaurant electrical work clusters around kitchen, hood, refrigeration, and customer-facing scope. This pillar links to specifics.
Three guides to read first
Browse the Full Library
Different restaurant formats have different electrical scope. Counter service is simplest; full-service with bar and extensive kitchen is most complex.
| Restaurant type | Typical circuit count | TI electrical cost |
|---|---|---|
| Coffee shop (no cooking) | 8 to 14 | $22,000 to $48,000 |
| Counter-service quick service | 18 to 28 | $48,000 to $95,000 |
| Fast-casual with limited cooking | 22 to 36 | $65,000 to $125,000 |
| Full-service no bar | 30 to 45 | $95,000 to $175,000 |
| Full-service with bar | 38 to 58 | $130,000 to $235,000 |
| Fine dining with extensive kitchen | 45 to 70 | $175,000 to $325,000 |
Restaurant electrical succeeds or fails on kitchen equipment coordination. Here's the sequence that prevents the spec mismatches we've seen at competitors.
Days 1–30
Operator finalizes kitchen equipment list with the kitchen vendor (Hobart, Vulcan, True, etc.). We require this BEFORE pulling electrical permit.
Days 31–60
We confirm voltage, amperage, and connection type for each piece of equipment directly with the vendor. Specs go into the permit application and the circuit design.
Days 61–90
Circuits installed to the documented specs during rough-in phase. Photos taken of every termination for the equipment vendor's reference at install.
California Mechanical Code 508.1.1 requires hood exhaust to interlock with cooking equipment. This isn't a 'nice to have' — it's gating for inspection and ultimately for health department signoff.
San Rafael restaurant client hired a non-restaurant-specialty contractor for TI electrical. Hood install completed, equipment installed, ready for inspection. Inspector finds no hood interlock — the fan runs on a separate switch from cooking equipment. Restaurant can't open.
We get the emergency call. Implementing the interlock retroactively requires running a relay-controlled contactor from the cooking equipment circuits to the hood fan circuit. Three days of work plus re-inspection.
Final outcome: 1-week opening delay, ~$45,000-$80,000 in lost opening-week revenue, plus the cost of the remediation. Doing it right the first time would have added $1,800 to the original TI bid.
Restaurant electrical has the highest stakes-per-dollar of any commercial scope. Three things to verify.
Restaurant electrical has subcategories — coffee shop is different from full-service with bar is different from fine dining. Ask for 2-3 recent references in your specific category within the past 18 months.
Familiarity with the specific equipment brands you're installing (Hobart, Vulcan, True, Bohn, etc.) prevents spec mismatches. Ask which vendors the contractor has coordinated with on recent jobs.
This guide reflects Towery Electric's professional standards as a California-licensed C-10 electrical contractor and is for general information. Site conditions, panel configurations, code amendments, and permit-authority requirements vary; final scoping, sizing, and code compliance for your specific address are determined on a paid site assessment. We follow California Electrical Code (Title 24, Part 3) and applicable NFPA 70 (NEC) editions adopted by your AHJ.