Charging at a detached Kentfield garage is usually a feeder question rather than a charger question. Most detached structures here already have power, but the feeder supplying them was commonly sized for lighting and a door opener rather than a continuous 40-amp load. Separate structures also carry their own disconnect, grounding and bonding requirements. C-10 licensed (CSLB #989290).
01Why the subpanel rating misleads people.
A garage subpanel with a 100-amp main looks encouraging. It is not evidence of anything on its own. That panel can only pass what the feeder from the main service delivers to it, and on a property where the garage was wired in the 1970s that feeder is frequently a small conductor sized for a light, a door opener and an outlet for a battery charger.
So the first job is tracing the feeder: where it originates, what size it is, and how far it runs. On properties that have been extended over decades the answer is rarely what the panel schedule claims, and occasionally the feeder turns out to be doing something nobody documented.
Once that is known, the arithmetic is straightforward. The feeder’s capacity, minus what the garage already draws, is what the charger can have.
02What a separate structure adds to the code picture.
Feeding a detached building is not the same as extending a circuit inside a house. There are requirements for a disconnecting means at the structure, for grounding and bonding arrangements that differ from those in the main building, and for how the feeder itself is protected along its run.
None of that is exotic, but it is the part where a general-purpose installer gets caught out. An existing detached-garage feed installed decades ago may predate the current arrangement entirely, which means upgrading it is also an opportunity to bring the structure’s grounding into line.
Where the existing feeder genuinely cannot carry the charger, the options are the usual three: upgrade the feeder, fit a lower-amperage unit, or use load management. On a mature property the feeder upgrade may involve trenching, which pushes the economics toward the other two more often than you would expect.
03The cheap answer people miss.
If the main service panel sits on the house wall closest to the garage, running a new dedicated circuit directly to the charger position can be less expensive than upgrading a long, undersized feeder — and it leaves the garage’s existing supply untouched.
That is worth checking before anyone prices a feeder replacement, because the two routes can differ by thousands of dollars in either direction depending on geometry. It is also why we walk the property rather than quoting from the panel schedule.
On larger estate parcels the calculus shifts again, since an existing feeder to a structure near the parking area can be the shortest path to a working charger even if it needs work.
04From first call to closed permit in Kentfield.
Three phases, and the honest version of each. Nothing here is a promised date we do not set ourselves.
- Days 1–7Site walk, load calculation, written estimate. Panel photographs and a conversation about the appliances get most jobs quoted; anything with real distance gets the route walked first. The calculation decides whether the charger is the whole job or just part of it.
- Days 7–21Permit filed, materials staged, date set. Filing happens on signature rather than the week of the install, which is the single habit that keeps a two-week job from becoming a five-week one. Materials get staged while it moves.
- Days 21–30Install, inspection, closed permit. Install, then inspection to the scope as filed. Where the jurisdiction offers a contractor inspection option we use it, and the permit closes onto the address record either way.
Two adjacent questions this page does not answer: ev charger kentfield and ev charger kent woodlands. Both sit under the full EV Charger Installation guide.
By Steven Lockhart
Reviewed by Alex Towery, C-10 #989290